2021 - Undergrounding

In 2021, the Company completed undergrounding of King Street and Alexander Avenue, replaced six structures on the 50KV East Coast line, upgraded the St Joseph feeder, reconfigured the Te Rahu 33kV line and built a new 66KV line along Otara road that will provide a future connection to Te Kaha via the company’s zone substation in Ōpōtiki.